Plumbing Installation - Keltech C2N363/600D Installation Manual

Tankless heater models c2n series
Table of Contents

Advertisement

Installation
2

Plumbing Installation

Components Needed:
• (2) Union 3/4"
• Shutoff Valve
• Pressure and Temperature Relief Valve (150 psi/10 bar)
• Y-Strainer (100 mesh) or Inline Filter (150 microns)
• (2) Gate or Ball Type Valves
• Drain pipe
• Water hammer arrestor (recommended)
• Elbows, nipples and fittings as needed
CAUTION To avoid damage to the electronics
or internal wiring, do not perform any
brazing or sweat soldering inside the
enclosure.
NOTICE! Failure to install proper filtration may
result in a flow switch malfunction.
NOTICE! To avoid water damage, install a drain
pipe from the pressure relief valve to
an unrestricted drain.
If end use fixture is not at the highest point in
the plumbing loop, then an automatic air vent
valve must be added at the highest point in the
system or at any drop to eliminate trapped air.
Dimensions, Plumbing and
Electrical Configurations
3/4"
Female
NPT Outlet
2"
10"
(51)
(254)
A
B
22-1/2" (572)
24" (610)
Bradley • 215-1821 Rev. B; ECN 16-17-005
3/4" Female
NPT Inlet
Optional Fused
Disconnect
Suggested
Location for
Power Entrance
- Provided By
Installer
A
Install shutoff valve above (upstream of) the heater .
inlet
Install one union on the water inlet side of the
heater . Install one 100 Mesh (150 micron) Y-strainer
above (upstream of) union .
Install one union on the water outlet side of the heater .
Install one P & T Relief Valve above (downstream of)
union .
B
Install the pressure relief valve (150 psi/10 bar) and
outlet plumbing of heater per code requirements and
route relief valve discharge to drain . Make sure no
shutoff valve is between the water heater outlet and
the relief valve, as well as no shutoff valve between
the relief valve discharge and drain . Install hammer
arrestor . Ensure plumbing is secure and not subject
to vibrations .
C
Use 3/4" hard copper tubing or pipe as needed .
Outlet
P&T Relief
Valve
3-3/8"
(86)
To Drain
8"
(203)
8-3/4"
Suggested Installation Configuration
(222)
Components provided by installer unless
otherwise specified . Reference the product
options sections or contact your local
Bradley Representative for product options .
5/3/2016
C2N Series Tankless Heater
Dim. "A"
Dim. "B"
36kW
31-1/2" (800)
30" (762)
50kW
37-1/2" (953)
36" (914)
Inlet
Ball Valves
Y-Strainer
Recommended
TEMPERATURE CONTROLLER
LOAD L
R
1
2
3
4
5
LOAD R
GROUND FAULT
READY
FAULT
TEST
RESET
Threaded
Unions
5

Advertisement

Table of Contents
loading

Table of Contents