Check points for test operation

1) Check if the boiler is installed correctly.
① Check if the floor surface is made of strong and flat non-flammable materials
such as concrete and if the surrounding area is also made of non-flammable
materials.
② Check the air intake and vent in the boiler room.
③ Check if the boiler room is provided with a drain, and if the boiler is equipped
with the drain valve.
④ Check if the boiler and the pipeline are heat insulated to prevent frost damage.
⑤ Check if the flue pipe is correctly installed.
⑥ Check if rain does not permeate through the penetration portion of the exhaust
pipe.
⑦ Check if the boiler is evenly installed.
⑧ Check if there is water leakage near the piping connection joint.
⑨ Check if there is any leakage near the gas pipe connection joint.
⑩ Check if the boiler room is equipped with the gas leak alarm device and the gas
breaker.
- The location of installation of the gas leak alarm device
LNG : 300mm from the ceiling
LPG : 300mm from the floor
⑪ Check if the fuel is the same as the gas specified on the name plate of the boiler.
⑫ Check if the pressure release pipe or the safety valve are installed in the boiler.
⑬ Check if the ground wire is connected. (If the ground connection is made on the
fuel pipe or the lightning rod, change the position.)
53

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the KDB-535GTD and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents