MITSUBISHI
ELECTRIC
3.0 INSTALLATION AND OPERATION
3.1 Transportation and Installation
TABLE 3.1 How to transport and install the system
Transportation
Transport unit with forklift.
Note : Do not transport in a horizontal position. Cabinets should be maintained upright within +/-
15° of the vertical during handling.
3.2 Handling
The UPS is shipped in export packaging. Remove the UPS from the package only when it is
ready for installation.
Note : The figure 3.1 export packaging is for 7.5kVA through 20kVA UPS only.
2033C SERIES UPS
OWNERS / TECHNICAL MANUAL
Pull out the UPS cabinet as shown in Figure 3.1
Fix the UPS unit in place using the four (4) leveling feet.
FIGURE 3.1 Handling
Leveling
feet
RAMP
Roof
during shipping
MITSUBISHI ELECTRIC 2033C SERIES UPS
Installation
2
1
5
4
3
of
the
package
Page Number:
3-1