C. Vertical Penetration Framing
WARNING
Fire Hazard
Keep loose materials or blown
insulation from touching the
vent pipe.
• National building codes recommend
using attic shield to keep loose materials/
blown insulation from contacting vent.
• Hearth & Home Technologies requires
the use of an attic shield.
Installing the Ceiling Firestop
• Frame an opening 10 inches by 10 inches
whenever the vent system penetrates a
ceiling/fl oor (see Figure 6.7).
• Frame the area with the same sized
lumber as used in ceiling/fl oor joist.
• When installing a top vent vertical
termination appliance the hole should be
directly above the appliance, unless the
fl ue is offset.
• Do not pack insulation around the vent.
Insulation must be kept away from the
pipe.
Installing Attic Shield
Note: An additional ceiling fi restop is not
required if attic shield is used.
• Frame opening for attic shield.
• Attic shield may be installed above or
below ceiling (see Figure 6.8).
• Secure with three fasteners on each
side.
• Fold tabs at top of attic shield in toward
vent pipe. Tabs must keep vent pipe
centered within shield.
• Field construct additional shield height if
insulation is deeper than height of attic
shield.
Heat & Glo • 8000TR-OAK, 8000TR-OAK-IPI, 8000TRLP-OAKIPI • 2057-900 Rev. K • 12/07
Figure 6.7
BEND TABS IN
AROUND PIPE
ATTIC SHIELD INSTALLED
BELOW CEILING
Figure 6.8 Installing the Attic Shield
ATTIC ABOVE
HOLE SHOULD MEASURE
10 IN. X 10 IN.
(254 MM X 254 MM)
INSIDE TO INSIDE
3 FASTENERS
PER SIDE
ATTIC SHIELD INSTALLED
ABOVE CEILING
10 IN. (254 MM)
10 IN.
(254 MM)
23