PERFORATED
DISCHARGE DUCT
FLANGE
Fig. 16—Duct Flanges
Step 3—Installation in Horizontal Applications
These furnaces can be installed horizontally in either horizontal
left or right discharge position. In a crawlspace, furnace can either
be hung from floor joist or installed on suitable blocks or pad.
Furnace can be suspended from each corner by hanger bolts and
ANGLE
IRON OR
EQUIVALENT
(B)
(A) ROD LOCATION
USING DIMPLE
LOCATORS
(SEE DIMENSIONAL
DWG FOR
LOCATIONS)
(A) PREFERRED ROD LOCATION
(B) ALTERNATE ROD LOCATION
NO
YES
210°
MIN
YES
A93029
(B)
(A)
3
/
-IN. HEX NUT
8
& WASHER (4)
REQD PER ROD
NOTES:
Fig. 17—Crawlspace Horizontal Application
angle iron supports. (See Fig. 17.) Cut hanger bolts (4 each 3/8-in.
all-thread rod) to desired length. Use 1 X 3/8-in. flat washers,
3/8-in. lockwashers, and 3/8-in. nuts on hanger rods as shown in
Fig. 17. Dimples are provided for hole locations. (See Fig. 2.)
The entire length of furnace MUST be supported when
furnace is used in a horizontal position to ensure proper
draining. When suspended, bottom brace supports sides and
center blower shelf. When unit is supported from the ground,
blocks or pad should support sides and center blower shelf
area.
"
3
5
4
DRAIN
(A)
(B)
13
/
-IN. MAX
16
(A)
(B)
ALTERNATE SUPPORT
LOCATION FROM BACK
1. A 1 In. clearance minimum between top of
furnace and combustible material.
2. The entire length of furnace must be
supported when furnace is used in horizontal
position to ensure proper drainage.
15
3
-IN. ROD
8
ALTERNATE SUPPORT
LOCATION 4-IN. MIN
8-IN. MAX
A93304