8 Functional Checks (Commissioning Part III)
• Yellow flame indicator (2) ON.
• Green warmstart indicator (3) FLASHING (hot water is
being drawn from the system).
Central Heating operation
• Operate the heating system.
If boiler is operating correctly, the status of the
indicators will be as follows:
• Red lock out indicator (1) OFF.
• Yellow flame indicator (2) ON (burner active).
• Green warmstart indicator (3) ON, OFF or FLASHING
(see above).
The LCD display indicates the flow temperature (in °C)
of the boiler in normal operation.
1
2
Fig. 8.2 Functional check turboMAX plus
8.3 Functional check of operation
(thermoCOMPACT only)
This boiler is fitted with indicator lights to display the
operating status of the boiler. The status of the
indicators in normal operation will be as follows.
Boiler in stand by mode
• Red lock out indicator (1) OFF.
• Yellow flame indicator (2) OFF.
• Green indicator (3) has no function.
Central Heating/hot water operation
• Operate the heating/hot water system.
If boiler is operating correctly, the status of the
indicators will be as follows:
• Red lock out indicator (1) OFF.
• Yellow flame indicator (2) ON (burner active).
• Green indicator (3) OFF.
The LCD display indicates the flow temperature (in °C)
of the boiler in normal operation.
1
2
Fig. 8.3 Functional check turboMAX plus
34
Supplied By www.heating spares.co Tel. 0161 620 6677

8.4 Adjusting pump speed

The unit is fitted with a two-speed pump. The pump is
delivered with the switch (1) set to position III (Fig. 8.4.).
It is possible, however, to change the pump setting from
Level III to Level II manually when there is noise coming
from the heating system.
Final system flush ("HOT")
• Turn on the boiler for central heating and allow the
• Check that the heating system is watertight.
3
• Turn the boiler off and rapidly drain both boiler and
• Refill the system and release all air. Release water
(The actual reading on the pressure gauge should
ideally be 0.5 bar plus an additional pressure
corresponding to the highest point of the system above
the base of the boiler - 10 m head equals an additional 1
bar reading on the pressure gauge. The minimum
pressure should not be less than 1 bar in any
installation.)
If the system is to be treated with an inhibitor it should
be applied at this stage in accordance with the
manufacturers instructions.
Further information can be obtained from Sentinel,
GE Betz. Widnes, Cheshire, WA8 8UD.
Tel: 0151 420 9595
or
Fernox, Alpha-Fry Technologies,
Tel: 0870 6015000.
• Disconnect the temporary filling connection.
• Refit the boiler casing.
• Attach the bottom cover to the boiler. It may be
3
Instructions for Installation and Servicing turboMAX plus and thermoCOMPACT R1
Attention!
Important note:
The boiler should only be operated at pump
setting III because the heating capacity for hot
water is reduced when operated at pump
setting II!
boiler and system to reach operating temperature.
system while still hot.
from the system until the system design pressure of
1.0 bar is attained.
necessary to apapt the bottom cover by removing the
easy break sections.