12-3 PCB Inspection Method

12-3-1 Pre-inspection Notices
1. Turn off the breaker, AC power source, before disassembling the unit because of electrical hazard.
2. Confirm the complete discharge of capacitor C102, C702, C703, C704, C705, C706, C707 on the INVERTER PCB when you touch the
PCB.Especially dischargeing speed of C702-C707 is very slow because of little load in stand-by condition. To confirm the voltae of
C702-C707, measure the DC link voltage at the IGBT module pins near C701 at which applying voltage(450-510Vdc) is marked.
To confirm discharging of C102, measure the voltage of non mounted C103 solder hole or check if all LEDs are off.
3. Don't touch the metal body of electrolytic capacitor for avoiding electrical shock before confirming discharge.
4. To discharging the capacitor use power resistor of about 1 Kohm 10W. Soldering tool(non electronic temperature control type) can
be used as a discharging resistor.
5. Don't pull the lead wire but hold the whole housing to disconnect or connect a housing from or to the PCB.
12-3-2 Inspection Procedure
1. Check the connection of each housing to the connector first and the peeling of PCB copper pattern.
2. The PCB is composed of the 3 part in the indoor unit.
1.
INDOOR Main PCB part : Indoor unit control, MICOM and surrounding circuit, relay, fan motor driving circuit,
1.
Display PCB part : LED lamps, Switch,Remocon module.
1.
INDOOR EMI PCB part : Line filter, Noise Capacitor and Varistor
3. The PCB is composed of the 3 part in the outdoor unit.
1.
EMI PCB part : Line filter for electrical noise, Varistors for surge and Fuses.
1.
MAIN PCB part : Refrigeration cycle controller with MICOM
1.
INVERTER PCB part : Compressor driving inverter and BLDC fan controller
12-3-3 Indoor Detailed Inspection Procedure
No
Procedure
Open the electronic
component box and
1
check the PCB fuse
Check the LEDs for
DC power and communi-
cation condition
2
Check the DIP and rotary
3
switch on the PCB
Check the DC voltage
4
FAN operation checking
Press the ON/OFF button.
5
1. FAN Speed[HIGH]
2. FAN mode
Samsung Electronics
sor reading circuit, buzzer driving circuit and DC power supplying circuit.
Inspection Method
Turn off the power
1) Is the Fuse F701 on the EMI PCB blown?
2) Is the Fuse F702 on the MAIN PCB blown?
Turn on the power
1) Is RED LED blinking?
1)
his led means micom is running normally.
2) Is GREEN LED blinking?
1)
This means communication between Indoor and
Outdoor unit is on
3) Is YELLOW LED blinking?
1)
This means communication between Indoor and
wired remote controller is on.
1)
It may take one minute to start communication
1) Is the setting of each switch proper?
1) Is the voltage of CN32 pin #1-#2 12V?
2) Is the voltage of C109 V?
1) Is the FAN motor running?
2) Is the connection of CN73 normal?
Cause
Over current
Indoor fan motor short
PCB AC Part pattern short
Communication ciucuit trouble
Communication wire connection trouble
wrong connection for power supply wire of
remote controller
Wrong setting of switch
SMPS on MAIN PBA trouble
Load short
Controller trouble inside of the fan motor
connector trouble of CN73
sen-
12-19