NOTE: Termination cap should pass through the wall firestop from
the exterior of the building. Adjust the termination cap to
its final exterior position on the building.
WARNING: Termination cap must be positioned so that arrow
is pointing up.
Attach the termination cap with the four wood screws provided.
Before attachment of the termination, run a bead of silicone sealant
rated above 250°F on its outside edge too, so as to make a seal
to the exterior wall.
NOTE: Wood screws can and should be replaced with appropriate
fasteners for use on stucco, brick, concrete or other types
of siding.
CAUTION: If exterior walls are finished with vinyl siding (or materials
that could become discolored or warp), it is necessary to install a
vinyl siding standoff.
The vinyl siding standoff will be installed between the vent termination
and the exterior wall. See Figure 51. This horizontal vent termination
bolts onto the flat portion of the vinyl siding standoff, so an air space
will exist between the wall and the termination cap.
For installations requiring a vertical rise on the exterior of the
building, 14-inch and 36-inch tall Snorkel Terminations, as shown in
Figure 52 are available. Follow the same installation procedures as
used for standard Horizontal Terminations. If the Snorkel Termination
must be installed below grade (i.e. basement applications, proper
drainage must be provided to prevent water from entering the
Snorkel Termination. See Figure 53. Do not attempt to enclose the
Snorkel within the wall or any other type of enclosure.
Page 34

HORIzONTAL TERMINATION

Figure 51
SNORKEL
Nat models
Figure 52
SNORKEL
ADEQUATE
DRAINAGE
Nat models only
Figure 53
12 INCHES
MINIMUM
12 INCHES
MINIMUM
26930-5-1010