Section 5 - ADJUSTMENTS
& REPAIR
5.8
MOWER SPINDLES (Field Serviceable Spindles)
BEARING REPLACEMENT
In the
event
that
a spindle
bearing
requires
replacement,
the
SNAPPER
Field
Serviceable
Spindles have been designed so that no special
tools or presses are required.
1. Remove belt. Loosen blade nut and remove.
Allow blade bolt, washer, blade and four spacers to
drop down out of the spindle housing. See Figure
5.19.
IMPORTANT:
Spindle
housing must be filled
with
grease
before
operating
mower.
Failure
to
fill
housing will cause premature bearing failure.
®
REMOVE NUT _O'_
REMOVE BELT
[
_
FROM SPINDLE
BLADE
FIGURE 5.19
2. Remove spindle pulley from spindle shaft.
3. Locate circular retaining ring on spindle shaft at
top bearing. Remove retaining ring. Allow spindle
shaft to drop out of housing.
4. Top and bottom bearings are now removable.
Pull out on inner race
to slide
bearing
from
housing. See Figure 5.20.
5. Thoroughly
clean
all parts removing
all old
contaminated grease.
6. Install new bottom bearing first.
7. NOTE: The bearing is sealed/shielded
on one
side only. The bottom bearing must be installed
with the sealedtshielded side DOWN.
8. Insert
spindle
shaft
up through
the
bottom
bearing. Slide spacer down over spindle shaft.
9. Install new top bearing. Install the top bearing
with the seallshield UP.
10. Slide circular retaining ring down spindle shaft
until it fully locks into groove on shaft.
11. Apply a generous amount of general-purpose
grease to the concave side of the nylos seal. Install
the nylos seal with concave greased side down.
12. Place spindle
pulley and spacer
on top of
spindle shaft.
13, Reinstall blade bolt, washer,
blade and four
spacers. See Figure 5.15
14. Torque blade bolt and nut to 70 to 80 ft. Ibs.
15, Pump grease into spindle housing until grease
purges from vent on housing.
16. After the first 5 hours of operation,
grease
spindle housing to insure it is full, then every 25
hours.
I
I
EARING
I
SEAL UP
DowNBEARING
SEAL
I
SPACER
GO
NYLOS SEAL
RETAINING
RING
BEARING
SPINDLE
HOUSING
i_P
SPACER
OO
BEARING
SPINDLE
SHAFT
FIGURE 5.20
28