Location - Gas Powered Steamers & Steam Generators; Gas Supply Connection - Vulcan-Hart VHX24 Series Installation & Operation Manual

Vhx24, vhl2, vhl3 & vh3616 series food steamers & mhb24 series steam generators
Hide thumbs Also See for VHX24 Series:
Table of Contents

Advertisement

Temperatures in the boiler can briefly reach as high as 212 F (
temperature of drain water be no greater than 140 F (
boilers, some provision for lowering the water temperature must be provided by the user or installer
to meet this code requirement.
LOCATION — GAS POWERED STEAMERS & STEAM GENERATORS
The equipment area must be kept free and clear of combustible substances.
The recommended clearance for proper operation is 36" (
from combustible or non-combustible construction is 0" at the sides and back. The recommended
clearance for service access is 18" (
Do not obstruct the flow of combustion and ventilation air. Adequate clearance for air openings into
the combustion chamber must be provided. Make sure there is an adequate supply of air in the room
to replace air taken out by the ventilating system. If you have any questions, contact the ventilation
system installer.
An exhaust system should be located directly above the steamer to exhaust steam, flue exhaust and
heat generated by the steamer.
Do not permit fans to blow directly at the steamer. Avoid wall-type fans which create air crosscurrents
within the room.
Avoid open windows next to the steamer.
IMPORTANT: Do not locate the boiler base directly over a drain.

GAS SUPPLY CONNECTION

All gas supply connections and any pipe joint compound used must be resistant to the action of propane
gases. A 1" (
) minimum inside diameter gas supply line is required. If quick-disconnect devices
2.5 cm
are used, make sure they are rated to meet or exceed the required 270,000 BTU/Hr rate. Make sure
the pipes are clean and free of obstructions. Codes require that a gas shutoff valve be installed in the
gas line ahead of the steamer.
The burner is equipped with fixed gas and air orifices for use with natural or propane gas.
The gas line must be capable of delivering gas to the boiler without excessive pressure drop at the
minimum 270,000 BTU/Hr rate specified on the rating plate. Inadequate gas supply would result in
burner noise and poor burner performance. An indication of inadequate supply would be evidenced
1
by a
/
" W.C. or greater reduction in pilot burner pressure when the main burner comes on.
4
The boiler is equipped with a factory-preset pressure regulator.
manometer at time of installation to verify that they agree with the pressures in the table, below.
GAS TYPE
Natural
Propane
WARNING: PRIOR TO LIGHTING, CHECK ALL JOINTS IN THE GAS SUPPLY LINE FOR LEAKS.
USE SOAP AND WATER SOLUTION. DO NOT USE AN OPEN FLAME.
After piping has been checked for leaks, all piping receiving gas should be fully purged to remove air.
) at the sides and back.
45.7 cm
GAS SUPPLY PRESSURES
Line Pressure
Minimum
Maximum
7.0" W. C.
14.0" W.C.
(
)
(
1.75 kPa
3.5 kPa
11.0" W.C.
14.0" W.C.
(
)
(
2.7 kPa
3.5 kPa
100 C
). At the end of the day, when purging the
60 C
) at the front. The required clearance
91.4 cm
Main Boiler
Valve Pressure
3.0" W.C.
)
(
0.75 kPa
3.0" W.C.
)
(
0.75 kPa
– 7 –
). Local codes require that the
Check gas pressures with a
Pilot Valve
Pressure
3.5" W.C.
)
(
)
0.88 kPa
3.5" W.C.
)
(
)
0.88 kPa