Site Preparation Checklist

S e n d d o c u m e n t a t i o n c o m m e n t s t o m d s f e e d b a c k - d o c @ c i s c o . c o m
Table D-1
Site Planning Checklist
Task No.
Planning Activity
1
Space evaluation:
Space and layout
Floor covering
Impact and vibration
Lighting
Maintenance access
2
Environmental evaluation:
Ambient temperature
Humidity
Altitude
Atmospheric contamination
Air flow
3
Power evaluation:
Input power type
Power receptacles
Receptacle proximity to the equipment
Dedicated circuit for power supply
Dedicated (separate) circuits for redundant
power supplies
2
UPS
for power failures
4
Grounding evaluation:
Circuit breaker size
CO ground (AC- powered systems)
5
Cable and interface equipment evaluation:
Cable type
Connector type
Cable distance limitations
Interface equipment (transceivers)
6
Electromagnetic interference (EMI) evaluation:
Distance limitations for signaling
Site wiring
3
RFI
levels
1. Verify that the power supply installed in the chassis has a dedicated AC source circuit.
2. UPS = uninterruptible power supply.
3. RFI = radio frequency interference.
Cisco MDS 9100 Series Hardware Installation Guide
D-2
1
Appendix D
Verified By
Time
Site Planning and Maintenance Records
Date
OL-21514-01