Critical Notes - Panasonic REHP-KY-CO2-160GL Install Manual

Reclaim energy heat pump hot water system
Table of Contents

Advertisement

CRITICAL NOTES

NOTE 1
Remember to drain and purge the heat pump on
commissioning (otherwise system might fail)
– Refer to "Drain Plug" diagram shown below.
Also, remember to drain from the hot water taps
inside the house.
4
Bottom board
Drain elbow
Drain hose
(Inner diameter is 15 mm or 16 mm)
Be careful not to let the drain hose
come off.
Gap*
6
Reclaim Energy |
Provide a gap
for the spout to
indirectly drain.
(Do not let it
submerge in
water)
Install the heat pump
unit on a stand with
a height of 100 mm or
more and make the drain
hose slope downwards.
15 A
COLD
MAINS
Quick Start/Install Manual – v1.0
NOTE 2
The sensor probe must be fully inserted and
secured (using gland or silicon plug) in the bottom
tank sensor. The sensor cable comes with a rubber
sleeve. Fully push the sensor in and then push the
cable sleeve until only 6 mm is protruding. Then
tighten up the gland so the sensor is firmly secure.
NOTE 3
Maximum horizontal distance is 0m and
vertical distance is 3m between heat pump
and tank (max of 5 bends)
58 °C
PWR
TEMP
HP ON
BOOST
FAULT
ERROR
HEAT PUMP CONTROL V2.0
BOOST
TEMP
MENU
EXIT
ENTER
Temperature Sensor
v1.1. controller
RJ 45 cable
To stop back-flow from tank to heat
pump, it is recommended to use a
swing check valve between heat pump
flow and tank hot water inlet if heat
pump installed is above the tank level.
Hot Outlet: 63c
Cold Inlet
Heat Pump Unit
PLV 500 kPa
local plumber - not mandatory
from system perspective.)
Heat Pump
Return Port
Tempering Valve
Storage Tank
PTRV:
850 kPa
Thermistor
Heat Pump
Flow Port
ECV
LOAD

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rehp-ky-co2-250glRehp-ky-co2-315glRehp-ky-co2-400glReclaim energy rehp-ky-co2-160glReclaim energy rehp-ky-co2-250glReclaim energy rehp-ky-co2-315gl ... Show all

Table of Contents