CHECKLIST

ITEM
CHECK
GENERAL
Water supply is in accordance with water quality standard.
There is no leakage from the pipes.
There is no flammable hazardous materials around the unit.
6
6
2
There is no damage, deformation, or contamination to any components.
There is enough space for inspection / repair of each component?
The floor below the tank/heat pump has been properly waterproofed and can support the component.
Hot water is available with enough pressure at the taps inside the house.
HEAT PUMP
The heat pump unit has been installed properly in line with these guidelines.
The drain plug is properly closed
The drain of heat pump unit is in the correct position to drain.
A two-step air purge operation has been completed successfully.
The wiring cover on the heat pump is correctly closed.
TANK
The operation of PTRV is normal.
The tank is fixed in place with anchor bolts if necessary.
PIPING/WIRING
The mains breaker is of the correct size and voltage Breaker can be turned off, local disconnect is in
place. The movement of circuit breaker is correct.
Power supply wiring, ground wire, and "On/Off RJ45 cables" are fixed firmly.
Union joints are used so that the parts can be easily removed.
The insulation work for piping has been conducted properly.
CONTROLLER
Check all 3 connections are correctly firm and in place: 1 – communication (RJ45 patch or Modbus)
cable to heat pump unit, 2 – Sensor cable to tank, 3 – Power is connected.
Correct time of day has been set up on the first powering.
Controller operational mode (OPTION modes) has been set up with reference to the customer
requirements.
27
Quick Start/Install Manual – v1.0
| Reclaim Energy
RECLAIMENERGY.COM.AU

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rehp-ky-co2-250glRehp-ky-co2-315glRehp-ky-co2-400gl

Table of Contents