Carrier 61CW-Z Installation, Operation And Maintenance Instructions page 10

Table of Contents

Advertisement

4 - INSTALLATION
To ensure this, install pressure relief devices in the pipework and 
service/check  them  regularly.  Ensure  that  there  are  no  shut-off  
valves in the pipework between the heat pump connection and 
the next pressure relief devices.
In addition to the mass flow to be dumped by the operator in an 
emergency, the pressure relief device must additionally be able 
to  dump  a  mass  flow  corresponding  to  the  required  minimum 
refrigerant blow-down capacity Qmd (see safety valve calculation 
in section 10).
The  heat  pump  must  be  operated  only  within  the  permissible 
limits of use (see appendix). The system installer/operator must 
ensure that the limits of use are maintained. 
The temperature of the heat transfer medium at the evaporator
outlet must not fall below 4°C.
When selecting and sizing lines, observe the applicable general 
and  national  standards,  conditions  and  guidelines.  The  latest 
applicable engineering standards must be taken into account and 
observed.
We recommend hydraulic separation of the heat pump and heat 
source. This separation can be achieved with a separate heating 
circuit connected to a low loss header or buffer tank. On the source 
side  (evaporator),  ensure  sufficient  buffer  volume  –  at  least  15 
litres per kW of cooling capacity. A smaller buffer tank can only be 
used in exceptional cases and at the user's own risk if the energy 
supply and flow rate through the heat pump heat exchanger are 
permanently constant.
The operating point (temperatures, flow rates) agreed in the
system datasheet must be ensured.
In any case, at least the minimum and maximum flow rate through 
the evaporator as specified in the machine data (see appendix) 
must be maintained during heat pump operation. The flow rate 
must lie within the specified minimum and maximum values. 
The parameters specified in the system datasheets (in particular 
temperatures, temperature spreads, flow rate) must be met during 
heat pump operation. Modified system parameters can result in 
different heat pump outputs and/or temperatures. 
If CARRIER is not notified of a specific operating point/specific 
temperature spread in good time, the heat pump will normally be 
sized with temperature differentials of 4–5 K between evaporator 
inlet and outlet. In this case these values will have to be maintained 
during heat pump operation.
As standard, the heat exchanger connections are Flange unions.
Ensure that these connections are not reversed. For the position 
of these connections (inlets and outlets), see the dimensions sheet 
in  the  appendix.  The  inlet  and  outlet  are  also  labelled  on  the 
evaporator. The connections must be tension-free and be made 
with anti-vibration fittings.
When  installing  pipework,  take  care  to  avoid  transmission  of 
structure-borne sound. 
When sizing the source circulation pump, the internal pressure 
differential  of  the  heat  pump  evaporator  must  be  taken  into 
account (in accordance with the operating point data). 
10
Use only suitable media in the evaporator circuit. The limit values 
specified in Table 1 must always be observed.
Ensure that no dirt or foreign bodies can enter the evaporator. We 
strongly recommend that you install a filter, dirt separator, or at 
least a filter strainer, upstream of the evaporator inlet.
Ensure that the filter is easily accessible and regularly cleaned. A 
clogged strainer significantly impairs heat transfer and can cause 
a  safety  shutdown.  Install  valves  and  thermometers  in  the  flow 
and return lines to allow continuous monitoring of the water/brine 
flow rate and the heat pump operating state. At the lowest point 
in the pipework, fit a drain pipe to allow the system to be drained. 
Size the pipework according to the heat pump specification.
The flow velocity in the pipework should not exceed 1 m/s (noise/
pressure drop).
Regarding  the  temperature  spread,  please  note  the  need  for 
source buffer tank charging: assuming that the source buffer tank 
has been fully cooled to the required temperature, the heat pump 
must then be stopped (via remote ON/OFF) until the buffer tank 
has charged up again sufficiently or the system can operate at the 
design  temperature  spread  again.  If,  for  example,  the  set 
temperature  is  10°C  and  the  temperature  spread  between 
evaporator inlet and evaporator outlet is 5 K, the heat pump should 
run only when the temperature at the condenser inlet is 15°C or 
more (see also section 6.2).
Before commissioning the heat pump, ensure that the evaporator 
circuit contains no air or other gases and the system has reached 
operating pressure.
CAUTION! The water or brine quality must be regularly
checked. Incrustations or acidic deposits could impair the
condition and function of the heat exchanger.
CAUTION! Impermissible media and substances they may
contain can destroy the components in the hydraulic circuit.
Excessively hard water/brine can result in deposits on the pipe 
inner  surfaces,  which  could  impair  the  heat  exchanger 
performance.
The  heat  exchanger  must  not  be  exposed  to  dynamic  or  local 
loads. Dynamic excess pressure and water hammer can damage 
the heat exchanger.
Exceeding  the highest permissible  flow rate can  cause  erosion 
and damage the evaporator.
After  draining  the  evaporator  water  or  brine  circuit,  always 
thoroughly dry the evaporator tubes to prevent corrosion.
Pump cavitation and gas in the hydraulic circuit must be prevented.
During prolonged idle times, completely charge the heat exchanger 
or fully drain and dry it.
WARNING! Never open the heat exchanger under pressure.
Risk of scalding.

Advertisement

Table of Contents
loading

Table of Contents