Power Source Confirmation; Installation Instruction; Installation Procedure - Delta SEG-48100-02I Operation Manual

48v 3u lithium-ion battery module
Table of Contents

Advertisement

3.4

Power Source Confirmation

Check that the device properties directly connected to the battery are user equipment,
switching power supplies, or other power devices.
Check the position of the DC interface in the device and the output voltage to see if it
meets the voltage requirements.
Check that the maximum output current of the DC device interface matches the selected
battery.
Check the maximum operating current of the battery-operated device and ensure that the
current is less than the maximum discharge current of the product being used.
Check and confirm the working ground position of the power system in the equipment
room.
3.5

Installation Instruction

Installation should pay attention to the following matters:
Mounting space and support weight. Make sure the battery has enough space for
installation, and make sure that the battery mounting bracket or cabinet can withstand the
battery's gravity.
Make sure that the power cable meets the maximum current requirement for the device to
operate.
Ensure that the power equipment, batteries and other assembly locations are reasonable
during the entire construction process.
Ensure that the wiring is reasonable and orderly; consider moisture protection and
corrosion protection.
The Installation site should be operated by at least two people
Waring !
Before installation, please ensure that the site meets the requirements of the installation
environment.
3.6

Installation Procedure

System Power-off
Before installing the battery, make sure that the battery is turned off and disconnect the
power supply of the device that needs to be connected to the battery to ensure that the
installation process is not powered
10