Trane Performance Climate Changer UCCA Series Installation, Operation And Maintenance Manual page 40

Table of Contents

Advertisement

Coil Piping and Connections
NOTICE
Breaker Cracking Pressure!
Failure to follow these instructions could result in
equipment damage. The 1/2-in. NPT, 15 degree swing
check valve vacuum breaker is recommended because
other vacuum breakers, such as spring-loaded ball-
check breakers, have cracking pressures as high as
1.25 inches Hg (17 inches of water). Vacuum breakers
with fitting sizes smaller than 1/2 in. NPT are too small
to relieve vacuum quick enough to ensure complete
condensate drainage. Other types of swing check valve
vacuum breakers are acceptable if the fittings size is
not smaller than 1/2-in. NPT and the cracking pressure
is not larger than 0.25 inches HG (3.5 inches of water).
To prevent coil damage, complete the following
recommendations:
Install a 1/2-in. NPT, 15 degree swing check valve vacuum
breaker with cracking pressure of 0.25 inches Hg (3.4
inches water) or lower at the top of the coil. This vacuum
breaker should be installed as close to the coil as possible.
For coil type NS, install the vacuum breaker in the unused
condensate return tapping at the top of the coil.
Vent the vacuum breaker line to atmosphere or connect it
into the return main at the discharge side of the steam trap
Note: Vacuum breaker relief is mandatory when the coil is
controlled by a modulating steam supply or automatic
two position (ON-OFF) steam supply valve. Vacuum
breaker relief is also recommended when face-and-
bypass control is used.
NOTICE
Coil Condensate!
Failure to follow these instructions could result in
equipment damage. Condensate must flow freely from
the coil at all times to prevent coil damage from water
hammer, unequal thermal stresses, freeze-up and/or
corrosion. In all steam coil installations, the condensate
return connections must be at the low point of the coil.
40
Proper steam trap installation is necessary for satisfactory coil
performance and service life. For steam trap installation:
1. Install the steam trap discharge 12 inches below the
condensate return connection. Twelve inches provides
sufficient hydrostatic head pressure to overcome trap
losses and ensures complete condensate removal.
a. Use float and thermostatic traps with atmospheric
pressure gravity condensate return, with automatic
controls, or where the possibility of low-pressure supply
steam exists. (Float and thermostatic traps are
recommended because of gravity drain and continuous
discharge operation.)
b. Use bucket traps only when the supply steam is not
modulated and is 25 psig or higher.
Note: Trane steam coils require a minimum of 2 psi of
pressure to assure even heat distribution.
2. Trap each coil separately to prevent holding up
condensate in one or more of the coils.
3. Install strainers as close as possible to the inlet side of the
trap.
4. If installing coils in series airflow, control each coil bank
independently with an automatic steam-control valve. Size
the traps for each coil using the capacity of the first coil in
direction of airflow.
5. Use a modulating valve that has linear flow characteristics
to obtain gradual modulation of the coil steam supply.
Note: Do not modulate systems with overhead or
pressurized returns unless the condensate is drained
by gravity into a receiver, vented to atmosphere, and
returned to the condensate pump.
6. Pitch all supply and return steam piping down 1 in. for
every 10 feet in the direction of the steam or condensate
flow.
Note: Do not drain the steam mains or take-offs through the
coils. Drain the mains ahead of the coils through a
steam trap to the return line.
7. Ensure overhead returns have 1 psig of pressure at the
steam trap discharge for every 2 feet of elevation for
continuous condensate removal.
CLCH-SVX009L-EN

Advertisement

Table of Contents
loading

Table of Contents