7. Testing
☐ Dry nitrogen available for pressure testing
☐ Trace gas amounts of refrigerant available for leak
testing, if necessary
8. Refrigerant on job site (if nitrogen charge option,
model number digit 16 = F, is chosen)
9. Systems can be operated under load conditions
10. Heaters
☐ If unit was factory charged (model number digit 16
= E), energize heaters for 24 hours prior to start-up.
Important: Chiller heaters must be energized a
minimum of 24 hours prior to start-
up. Chiller should have power
applied for this amount of time
before Trane Service arrives for
start-up.
☐ If unit has nitrogen charge (model number digit 16 =
F), contact Trane Service for unit charging prior to
start-up.
Important: Do NOT apply shore/service power to unit
with nitrogen charge. Shore/service power
will drive EXV valves, inhibiting ability to
adequately Vac and charge unit.
11. Owner Awareness
☐ Does the owner have a copy of the MSDS for
refrigerant?
Note: Additional time required to properly complete the
start-up and commissioning, due to any
incompleteness of the installation, will be invoiced at
prevailing rates.
AC-SVX003A-EN
This is to certify that the Trane® equipment has been
properly and completely installed, and that the applicable
items listed above have been satisfactorily completed.
Checklist
completed by:
________________________________
Signed:
________________________________
Date:
________________________________
In accordance with your quotation and our purchase order
number __________________, we will therefore require
the presence of Trane service on this site, for the purpose
of start-up and commissioning, by __________________
(date).
Note: Minimum two-week advance notification is required
to allow scheduling of the chiller start-up.
Additional Comments/Instructions:
Note: A copy of this completed from must be submitted to
the Trane Service Office that will be responsible for
start-up of chiller.
Log and Check Sheets