Combustible Air Inlet For Sealed-Chamber - Cadel SOUND3 5 UP Installer Manual

Table of Contents

Advertisement

Below 15 kW:
Air duct diameter
50 mm
60 mm
80 mm
100 mm
Above 15 kW:
Air duct diameter
50 mm
60 mm
80 mm
100 mm
Fig. 7 - Direct air inflow
4.2
COMBUSTIBLE AIR INLET FOR SEALED-CHAMBER INSTALLATION
How to connect to the stove in the sealed chamber with concentric system:
• Connect the air intake pipe to the combustion air pipe of the stove and tighten everything with a clamp (see [Fig. 9).
8
Maximum length (smooth duct)
2 m
3 m
7 m
12 m
Maximum length (smooth duct)
-
1 m
3 m
7 m
LEGEND
Fig. 7|Fig. 8
1
Room to ventilate
2
External air inlet
4
Shield grid
5
Curve inlet to turn downwards
Maximum length (corrugated duct)
1 m
2 m
4 m
9 m
Maximum length (corrugated duct)
-
-
1 m
4 m
Fig. 8 - Air inlet for sealed-chamber installation
Fig. 9 - Phase1
Stufe a pellet