Gas Connection - Southbend 3230 Owner's Manual

Radiant broiler
Hide thumbs Also See for 3230:
Table of Contents

Advertisement

\
INSTALLATION
GAS CONNECTION:
On most units the 3/4" NPT pipe nipple with union will be factory installed.
If it is on your unit, omit
Steps 1 to 4 below.
1. Locate the sheet metal cover plate on the bottom right of the unit. Remove the four screws which
hold it in place. A 3/8" NPT pipe with half of a union will now be exposed.
2. Packed separately in the unit is a pipe nipple with the mating half of the union attached. Locate
this pipe.
3. Insert the nipple, with half of the union attached, through the hole at the right rear of the unit.
On units mounted on sectional flue risers, the nipple must also be inserted through
the hole in
the riser. Tighten the two halves of the union together to make a gas tight seal.
4. Replace the bottom cover plate with the four screws.
5. Locate the pressure regulator
and reducing bushing packed in the unit. Connect the gas supply
line to the inlet of the pressure regulator (see arrow on body of regulator).
Connect the outlet of
the pressure regulator to the inlet of the unit as required by the particular
installation.
6. If applicable,
the vent line from the gas appliance
pressure regulator
shall be installed
to the
outdoors in accordance with local codes or, in the absence of local codes, with the National
Fuel
Gas Code, ANSI 2223.1-1988. Canadian installation
must comply with CAN/CGA-B149.1
Natural
Gas Installation
Code. Code CAN/CGA-B149.2
Propane Installation
Code.
NOTE:
Pipe joint compound must be suitable for use with LP gas.
WARNING:
IN THE EVENT A GAS ODOR IS DETECTED,
SHUT DOWN EQUIPMENT
AT
THE MAIN SHUTOFF
VALVE AND CONTACT
THE LOCAL
GAS COMPANY
OR GAS SUPPLIER
FOR SERVICE.
BROILER CERAMICS:
The broiler ceramic tiles are packed in the unit and must be installed before operating. To install:
1. Remove rack and drip pan.
2. Locate the ceramic tiles (12), bar burners (2) and the sheet metal channels (2) packed in the unit
and unwrap.
3. Install
the rear burner. There is an
orifice in the unit on each side of the
burner area. The orifice for the rear
burner is at the left side. Insert the
center opening of the air mixer cap
over this orifice and put the burner
lug at the opposite end of the burner
into the hole in the support bracket
on the right side of the unit.
4. Install
the front burner in a similar
manner. The orifice is on the right
side however.
5. Place the sheet metal channels
as
covers over the burners.
(See Figure 4).
6. Install the ceramic tiles between the
burners, behind the rear burner and
in front of the front burner (4 tiles
each). The cones on the ceramic tiles
must be pointing
downward.
The
tiles are supported by the flanges of
the sheet metal channels
and the
flanges inside the unit at the front
and rear.
FIGURE 4
SALAMANDER
RADIANT BROILER
_ .-
SECTION ONE - INSTALLATION
PAGE 8
Litho in USA
2-94

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

3230aw3230w323oaS-36S-36aS-36aw ... Show all

Table of Contents