Chapter 2
Installing Device
1.
Review the relevant certification information for any regulatory requirements. For more information, refer to
Section 6.1,
"Approvals".
2.
Mount the device.
3.
Connect the failsafe alarm relay.
4.
Connect power to the device and ground the device to safety Earth.
5.
Connect the device to the network.
6.
Configure the device.
Section 2.2

Unpacking the Device

When unpacking the device, do the following:
1.
Inspect the package for damage before opening it.
2.
Visually inspect each item in the package for any physical damage.
3.
Verify all items are included.
IMPORTANT!
If any item is missing or damaged, contact Siemens for assistance.
Section 2.3

Mounting the Device

The RUGGEDCOM M2100F is designed for maximum mounting and display flexibility. It can be equipped with
connectors that allow it to be installed in a 48 cm (19 in) rack or directly on a panel.
IMPORTANT!
Heat generated by the device is channeled outwards from the enclosure. As such, it is recommended
that 2.5 cm (1 in) of space be maintained on all open sides of the device to allow for some
convectional airflow.
Forced airflow is not required. However, any increase in airflow will result in a reduction of ambient
temperature and improve the long-term reliability of all equipment mounted in the rack space.
NOTE
For detailed dimensions of the device with either rack or panel hardware installed, refer to
"Dimension
CONTENTS
Section 2.3.1, "Mounting the Device to a Rack"
Section 2.3.2, "Mounting the Device to a Panel"
8
Drawings".
RUGGEDCOM M2100F
Installation Guide
Section 5.8,
Unpacking the Device

Advertisement

Table of Contents
loading

Table of Contents