Flue Assembly Installation
1. Locate the collapsed flue assembly in the compartment
above the gas heat controls by removing the panel
screws. The assembly is secured by screws up through
the roof of the gas controls compartment roof.
2. Separate the pieces of the collapsed assembly and
then assemble the stack as shown in .
3. Insert the tube on the flue assembly into the hole
located in the vertical support for the heat section.
4. Butt both tube sections together and center the pipe
clamp over joint.
5. Using the pre-punch hole in the flue assembly,
extension, and the vertical support, install the
appropriate number of mounting brackets (Refer to the
installation instructions that ship with the flue
assembly.)
Figure 30. Gas heat piping penetration locations
2.5M & 1.8M (W=16 1/8in, D=14 11/16in)
1.1M, 0.8M
(W=9 15/16in, D=9 12/16in)
Unit end plane
Edge of mist eliminator
46
Top View
B
C
K
H
Side View
Figure 29. Flue assembly
Flue
Extension
Vent Cap
Assembly
Heat Section
Vertical Support
Ø3
7
D
1
8
W
5
11
8
21
19
Condensate drain outlet
Pipe type: cpvc
Mounting
Bracket
Flue Tube
Hole at the base
7
20
16
Horizontal gas pipe inlet
Pipe type: Black pipe, sch 40