Mount Power Center Banks To Wall
4. Mount and secure both the CPC103 and CPC203 power center
banks to the wall using six (6) screws for each bank
(screws not provided in kit).
5. Remove the cover retaining screw and remove the cover from
upper side left PRIMARY power center and the lower left side
SECONDARY power center.
Connect AC Power Wires and ORP Sensor
Wires
1. Mount a JUNCTION BOX on the left side
of the Power Center Banks.
2. Run a CONDUIT (with 208VAC - 260VAC
wires) from the AC BREAKER to the
junction box. Note: This AC power should
be on its own breaker for future servicing.
Note: For 110VAC operations, each
power center will need to be re-
configured. A 110VAC wiring diagram is
provided on the inside of each the power
center covers.
3. Run conduit from the junction box into each
of the power centers located on the left side
(PRIMARY and SECONDARY). A (knock-
out) conduit opening is provided on the
bottom of each of power centers.
(Continued)
Remove
cover screw
and cover
Mount power center bank
to wall using six (6)
Remove cover screw and cover
Mount power center bank to wall
using six (6) screws
IntelliChlor Electronic Chlorine Generator COMSYS-12 Installation Guide
screws
Knock-out
opening for
conduit
3
CPC103
CPC203
CPC103
CPC203