Finishing the outdoor unit installation

10 Finishing the outdoor unit installation

10.1 To finish the outdoor unit installation

10.2 To close the outdoor unit

Installer reference guide
54
DANGER: RISK OF ELECTROCUTION
Make sure that the system is earthed properly.
Turn OFF the power supply before servicing.
Install the switch box cover before turning ON the power supply.
NOTICE
It is recommended that the refrigerant piping between indoor and outdoor unit is
installed in a ducting or the refrigerant piping is wrapped with finishing tape.
1 Insulate and fix the refrigerant piping and cables as follows:
d
c
a
b
g
a Gas pipe
b Gas pipe insulation
c Interconnection cable
d Field wiring (if applicable)
e Liquid pipe
f Liquid pipe insulation
g Finishing tape
2 Install the service cover.
NOTICE
When closing the outdoor unit cover, make sure that the tightening torque does NOT
exceed 4.1 N•m.
NOTICE
When closing the outdoor unit cover, make sure that the tightening torque does NOT
exceed 1.3 N•m.
e
f
1
2
1
2
2
RXF50~71D5V1B
R32 split series
4P519439-15Q – 2021.10

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rxf60d5v1bRxf71d5v1b

Table of Contents