The maintenance chart below indicates the components that should be checked while performing routine
maintenance on the dryer. The chart also indicates how often a specific check should be done.
Refrigerated Series Maintenance Schedule
Part
Coalescing Filter
Element
Condensing Coil
(AC units)
Condenser (WC
Units)
Drain Line Y-Strainer
High Pressure Switch
Low Pressure Switch
Fan Control
Switches (AC units)
Compressor Oil Level
Drain Solenoid
Oil Separator Element
**Oil separator element should be changed 24-48 hours after initial start-up.

6.1. Maintenance Procedures

Before performing any maintenance on the machine ensure that air pressure is vented from the system.
CAUTION
Also make sure that personnel performing the maintenance have read the maintenance section of the manual.
Some of the maintenance tasks will require the refrigeration system to run, but when not required,
turn the unit off before proceeding. Refer to lock-out/tag-out procedures.
Upon completion of the maintenance tasks be sure that the machine has been properly reassembled prior
to restarting and reintroducing air.
Weekly
Monthly
Biannually
Check
Check/
Check/
Check/
Clean
Clean
Clean
Check/
Check/
Check/
Clean
Clean
Clean
Check
Check
Check
Check
Check
Check
Check
Check
Check
Check/
Check/
Clean
Clean
Annually
Replace
Check/
Clean
Check/
Clean**
Check/
Clean
Check
Check
Check
Check
Check/
Clean
Check -
change at
20 PSID
64