DETAILED INSTALLATION STEPS

The appliance is shipped with all gas controls
and components installed and pre-wired. Re-
move the shipping carton, exposing the front
glass door. Remove the top and bottom louvered
control panel per instructions on Page 27 (see
Control Compartment Access / Louver Panel
Instructions). Remove the cardboard from
underneath the pressure relief plates, in area
behind top louver panel (see Figure 11). Open
the two latches (located under the firebox floor)
securing the glass door. Remove the door by
tilting it outward at the bottom and lifting it up.
Set the door aside protecting it from inadvertent
damage. See Figure 54 on Page 30.
Pressure Relief Plates
Remove Cardboard Before
Using Appliance
Figure 11

TYPICAL INSTALLATION SEQUENCE

The typical sequence of installation follows,
however, each installation is unique resulting
in variations to those described.
See the Page numbers references in the follow-
ing steps for detailed procedures.
Step 1. (Page 10) Construct the appliance
framing. Position the appliance within the
framing and secure with nailing brackets.
Step 2. (Page 10) Route gas supply line to
appliance location.
Step 3. (Page 13) Install the vent system and
exterior termination.
10
Step 4. (Page 25) Field Wiring
a. Millivolt Appliances – Install the operating
control switch (not factory provided) and
bring in electrical service line for forced air
circulating blower (optional equipment).
b. Electronic Appliances – Field wire and install
operating control switch.
Step 5. (Page 25) Install blower kit (optional
equipment).
Step 6. (Page 26) Make connection to gas sup-
ply.
Step 7. (Page 27) Checkout appliance operation.
Step 8. (Page 28) Install the logs, decorative
volcanic stone and glowing embers.
Step 9. (Page 30) Install glass door frame as-
sembly.
Step 10. (Page 30) Adjust burner to ensure proper
flame appearance.
Step 11. (Page 31) Install the hoods.

Step 1. FRAMING

Frame these appliances as illustrated in Figure
14 on Page 11, unless the appliance is to be
installed in a corner. See Figure 15 on Page
12 for corner framing installations. All framing
details must allow for a minimum clearance to
combustible framing members as shown in
Table 8 on Page 9.
If the appliance is to be elevated above floor
level, a solid continuous platform must be
constructed.
Headers may be in direct contact with the
appliance top spacers but must not be sup-
ported by them or notched to fit around them.
All construction above the appliance must be
self supporting. DO NOT use the appliance for
structural support.
The fireplace should be secured to the side framing
members using the unit's nailing flanges - one top
and bottom on each side of the fireplace front. See
Figure 12. Use 8d nails or their equivalent.
NOTE: DIAGRAMS & ILLUSTRATIONS NOT TO SCALE.
Unit Being Secured By Its Nailing Flanges
To The Framing
Figure 12

STEP 2. ROUTING GAS LINE

Route a 1/2" (13 mm) gas line along the inside
of the right side framing as shown in Tables.
Gas lines must be routed, constructed and made
of materials that are in strict accordance with
local codes and regulations. All appliances are
factory-equipped with a flexible gas line con-
nector and 1/2 inch shutoff valve. (See Step 6
on Page 26).
Right Side Front
Corner of Fire-
place Framing
6 1/2"
(152 mm)
Also see Figure 14.
Figure 13 -
ROUTE GAS LINE
Continued on Page 12.