Final System Setup

After completing all of the pre-start and startup
procedures outlined in the previous sections (i.e.,
operating the unit in each of its modes through all
available stages of cooling and heating), perform these
final checks before leaving the unit:
Program all user set points in the System Set Points
screen via the ROD.
Configure optional accessories in the System Setup
screen via the ROD.
Return the unit to normal operation by releasing all
overrides.
Set Date and Time via the Setup (Home Screen) via
the ROD.
Inspect the unit for misplaced tools, hardware, and
debris.
Verify that all exterior panels including the control
panel doors and condenser grilles are secured in
place.
Close the main disconnect switch or circuit protector
switch that provides the supply power to the unit's
terminal block or the unit mounted disconnect switch.
Verify that all overrides have been released.
42