I. PRELIMINARY INFORMATION
MODEL NO.:
DATE:
II. PRE-START-UP (insert checkmark in box as each item is completed)
VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT
VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS
CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
VERIFY THAT UNIT INSTALLATION IS LEVEL
CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND SETSCREW
TIGHTNESS
III. START-UP
ELECTRICAL
SUPPLY VOLTAGE
COMPRESSOR AMPS L1
INDOOR FAN AMPS
TEMPERATURES
OUTDOOR-AIR TEMPERATURE
RETURN-AIR TEMPERATURE
COOLING SUPPLY AIR
PRESSURES
REFRIGERANT SUCTION
REFRIGERANT DISCHARGE
VERIFY REFRIGERANT CHARGE USING CHARGING CHARTS ON PAGES 12 AND 13
Copyright 1997 Carrier Corporation
START-UP CHECKLIST
(Remove and Store in Job File)
L1-L2
L2-L3
L2
PSIG
PSIG
SERIAL NO.:
TECHNICIAN:
L3-L1
L3
DB
DB
WB
CL-1
CATALOG NO. 53PA-1Z0