Start-Up - Trane Flex II Series Installation Operation & Maintenance

Air-cooled chillers with fixed speed scroll compressors
Table of Contents

Advertisement

13

START-UP

13.1
PRELIMINARY CONTROLS
Before starting up the equipment it is very important to check that all the operations described in the paragraph
"CHECK LIST – MANDATORY OPERATION CONTROL BEFORE START UP" have been carried out correctly.
Moreover check that all the mechanical and electric equipment has been tightened perfectly. Particular attention
should be paid to the main components (compressor, exchangers, ventilators, electrical motors, and pump) if loose
fastenings are found tighten them well before starting up the machine.
The oil heaters have to be inserted at least 8 hours before starting up. Ensure that the compressors' carter is hot. Open
the compressor valve and the cooling circuit one, which may have been shut for charging. Control all the machinery
connected to the unit.