REQUIRED STEPS AFTER FINAL PLACEMENT

The compressor is secured to the base with two (2) bolts
for shipping. Although the unit will perform as
designed with the shipping bolts in place, there may be a
noticeable additional noise and vibration noted. To
obtain the lowest noise and vibration levels, remove the
shipping bolts after the unit is in its final operating
location. To gain access to the compressor, the
compressor access panel must be removed (Figure 7).
Once this panel is removed, the CRV/ERV air duct must
be removed. See Figure 4.
The air duct is removed by pulling it straight toward
you; there are no screws securing it in place. Both the
top and bottom slide toward you at the same time (pull
hard). Once removed, the compressor is visible as well
as the tags on the shipping bolts (Figure 3).
After the compressor shipping bolts have been removed,
the CRV/ERV air duct can be slid back in place and the
compressor access panel attached.

MINIMUM INSTALLATION HEIGHT

The minimum installation height to the bottom of the
roof or fixed ceiling for ducted applications is 9 ft. 7 in.
This provides enough clearance to install the duct work.
See Figure 5A.
The IWS Series wall sleeve has a built-in vertical
adjustment to fit window sill heights from 31-34 inches.
If additional height is required, two riser platform
accessories are available. The IRP3 increases the unit
height by 3 inches (Figure 5B) and the IRP6 by 6 inches
(Figure 5C).
2"
43 3/8"
1 11/16"

SECURING UNIT TO STRUCTURE

Shipped with the I-TEC unit is a wall mounting bracket
(screwed to shipping skid on backside of unit). This
bracket can be utilized to secure the top portion of the
unit to the wall using the appropriate field supplied
hardware based upon the material you are fastening to.
(There are several offset holes, sized to accept up to a
1/4" diameter fastener that will easily allow you to hit
studs on a framed wall.) See BRACKET SECTION
VIEW (Page 10) for locating this top wall bracket
which will need to be applied after the unit is located in
the final position.
Additional/optional mounting holes for up to a 3/8"
diameter fastener are also available in the backside of
the unit. These can be accessed by:
• removing the air filters for the uppermost set
• removing the compressor section service door for
the lower set
Refer to WOOD FRAMED INSTALLATION (Page 10)
for additional framing required to secure unit to wall.
The additional/optional mounting holes will require a
long extension to drive the fasteners.

WALL MOUNTING BRACKET LOCATION

BRACKET
Ø1/4"
3/4"
1 1/2"
7/8"
94" FROM BOTTOM
OF BRACKET TO
FLOOR WITHOUT
RISER KIT
MIS-3029
Manual
Page
2100-597
9 of 52