Further details regarding the individual steps
Status
Service
C
D
Commissioning the system
Danger
CO build-up as a result of incor-
rect burner adjustment can have
serious health implications.
Carry out a CO test before and
after work on gas appliances.
Tightness test
Gaskets on the boiler door and flue gas
components can be checked with an
inspection mirror during operation.
If required, remove the thermal insula-
tion components.
Traces of condensate on the outside of
the flue gas collector or on thermal insu-
lation components also indicate a leak.
R
S
E
F
Commissioning, inspection, maintenance
7. Press button S E to switch to the
operating display.
G
8. Press button R G.
The system will be restarted.
Note
Each time the system is restarted, the
setting parameters will be shown.
1 Max. output (70-100 %)
The output setting is unrestricted.
Base load can also be set (CS con-
figuration).
2 Gas type (NG = natural gas or LPG
= liquid gas)
3 Installation height (LA (low alti-
tude) or HA (high altitude))
(not available)
4 Temperature of the temperature
limiter
5 Integral value for minimum pause
time
6 Cycling protection method
Note
An examination of the burner setting with
the boiler heated to operating tempera-
ture (min. 40 °C) is essential.
Also check in the partial load range.
Boiler control unit service instruc-
tions
(cont.)