Twin rear bagger

Advertisement

3.
Install the upright support bracket onto the mounting
assembly on the tractor by hooking it over the mounting
assembly between the two tabs as indicated in (1) Figure 4-4.
4.
Secure the upright support bracket to the mounting
assembly in the proper mounting hole based on deck size,
with a 710-0376 hex bolt and 712-04063 flange lock nut
from hardware pack 689-00320. See (2) Figure 4-4.
1
2
2
Figure 4-4
5.
Install and secure the hanger assembly onto the upright
support bracket (3 in Figure 4-5) using a 710-0276 carriage
bolt and 712-04063 flange nut (4 in Figure 4-5) from
hardware pack 689-00320.
3
Figure 4-5
Note: The carriage bolt (710-0276), from hardware pack
689-00320, goes in the top hole with the nut facing the
engine. The hex bolt (710-0376), from the same hardware
pack, goes in the bottom hole.
42-inch Deck
46-inch Deck
4
Assembling Remaining Bagger Components
Now that the mounting brackets are assembled and are in place
on the tractor, follow these steps to assemble the remaining
bagger components.
1.
Snap the plastic upper chute support in place by first
clipping the side portion onto the bagger support rail (1)
with the edge of the snap feature aligned with the line on
the label, as shown in the inset of Figure 4-6.
2.
Snap the front side of the chute support to the rail (2), as
shown in Figure 4-6.
2
Figure 4-6
3.
If not already installed by the factory, install the
bagger screen into the bagger cover by first inserting one
end into the corresponding cutout mounting hole, as in
Figure 4-7. Make sure to feed the screen under the lip, as in
Figure 4-8.
Figure 4-7
S
ection
1
4 — A
& i
SSembly
nStAllAtion
9