Commissioning

Attention!
Only authorized and qualified specialists may commission the
peristaltic metering pump.
Attention!
Warning - risk of eye injury!
Chemical hazard! Wear safety goggles!
Attention!
Warning - risk of skin injury!
Chemical hazard! Wear protective gloves!
Attention!
Warning - risk of damage to clothing!
Chemical hazard! Wear protective clothing!
Procedure:
1 Place suction fittings into the filled chemical tank.
2 Check hose connections.
3 Open local ball valve if necessary.
4 Apply supply voltage.
Please note
®
The Chem-Ad
VPP and Chem-Ad
pumps start up as soon as the supply voltage is applied.
®
5 In Chem-Ad
the selected operating mode.
®
6 In Chem-Ad
The green light
to the set operating mode (see chapter 4.1.5).
7 When the hoses are completely filled with pumping medium,
check the entire dosing system for leakage.
8 Instruct operating personnel.
Chem-Ad
®
VPP / VPP-E / VPP-DC
®
VPP-DC peristaltic metering
VPP-E, provide for external signal depending on
VPP-E, ready the unit for dosing with the
stops flashing. Dosing proceeds according