Step 3 Install a partition board.
l Install a partition board between two half-width compute modules.
l Perform this operation only when no partition board is installed between two half-width compute
1.
2.
3.
4.
Step 4 Determine the position of the node. See
two lower slots of the chassis, corresponding to G530 V2-1 and G530 V2-2. The GP316s are
installed in the two upper slots of the chassis, corresponding to GP316-1 and GP316-2.
Issue 02 (2017-12-15)
Figure 4-14 Incorrect operations
NOTE
modules.
Press the air baffle in the chassis.
NOTE
The air baffle must be pressed during the entire installation process of the partition board.
Tilt the partition board to the chassis, align the positioning rod of the partition board with
the open slot at the bottom of the chassis, and push it in position. See (1), (2), and (3) in
Figure
4-15.
Figure 4-15 Installing a partition board
After the partition board is in position, release the air baffle. The air baffle automatically
pops up.
Tighten the five screws that secure the partition board to the top of the chassis and the
four screws that secure the partition board to the bottom of the chassis. See (4) and (5) in
Figure
4-15.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
4-16. The G530 V2 nodes are installed in the