GE T17 Installation Manual page 19

Ultrasonic flow transducer
Hide thumbs Also See for T17:
Table of Contents

Advertisement

2.2.3 Determining and Marking the Second Nozzle Location - Diametrical (cont.)
8. The new position of the center of the second nozzle is now identified as the intersection of the fold line and the
second edge of the strip of film (see Figure 15 below). Center punch this location prior to removing the film.
9. Remove the film from the pipe.
10. Scribe 6" long vertical and horizontal lines that intersect at the center-punch mark (see Figure 16 below).
Model T17 Installation Guide
Punch Here
Fold Mark
Side View
Figure 15: Center Punch the Second Nozzle Location
Scribe Lines
Figure 16: Making Scribe Lines
Chapter 2. Installing the Pipe Nozzles
Second Edge
Side View