Final System Set Up - Trane Foundation EBC180 Installation, Operation And Maintenance Manual

Packaged rooftop air conditioners cooling only and electric heat
Table of Contents

Advertisement

to the next component start-up procedure. Remove
electromechanical test mode connections.

Final System Set Up

After completing all of the pre-start and startup
procedures outlined in the previous sections (i.e.,
operating the unit in each of its modes through all
available stages of cooling and heating), perform these
final checks before leaving the unit:
☐ Program the Night Setback (NSB) panel (if
applicable) for proper unoccupied operation. Refer
to the programming instructions for the specific
panel.
RT-SVX50J-EN
☐ Verify that the Remote panel "System" selection
switch, "Fan" selection switch, and "Zone
Temperature" settings for automatic operation are
correct.
☐ Inspect the unit for misplaced tools, hardware, and
debris.
☐ Verify that all exterior panels including the control
panel doors and condenser grilles are secured in
place.
☐ Close the main disconnect switch or circuit
protector switch that provides the supply power to
the unit's terminal block or the unit mounted
disconnect switch.
S S t t a a r r t t U U p p