Start-Up

DANGER
Electric shock hazard. Can cause injury or death.
Before attempting to perform any service or
maintenance, turn the electrical power to unit to OFF
at disconnect switch(es). Unit may have multiple
power supplies.
WARNING
Use caution when removing access panels or other
unit components, especially while standing on a
ladder or other potentially unsteady base. Access
panels and unit components can be heavy and
serious injury may occur.
Do not operate energy core ventilator without the
filters and birdscreens installed. They prevent the
entry of foreign objects such as leaves, birds, etc.
CAUTION
Do not run unit during construction phase. Damage to
internal components may result and void warranty.
SPECIAL TOOLS REQUIRED
• Voltage Meter (with wire probes)
• Amperage Meter
• Thermometer
• Tachometer
• Incline Manometer or Equivalent
General Start-Up Information
Every installation requires a comprehensive start-up
to ensure proper operation of the unit. As part of that
process, the following checklist must be completed and
information recorded. Starting up the unit in accordance
with this checklist will not only ensure proper operation,
but will also provide valuable information to personnel
performing future maintenance. Should an issue arise
which requires factory assistance, this completed
document will allow unit experts to provide quicker
resolve. Qualified personnel should perform start-up to
ensure safe and proper practices are followed.
Unit Model Number _______________________________
Unit Serial Number _______________________________
(e.g. 04C99999 or 10111000)
Start-Up Date
_______________________________
Start-Up Personnel Name __________________________
Start-Up Company _______________________________
Phone Number
_______________________________
®
(e.g. ECV-10)
Pre Start-Up Checklist –
completed.
o Disconnect and lock-out all power switches
o Remove any foreign objects that are located in the
energy recovery unit.
o Check all fasteners, set-screws, and locking collars
on the fans, motor bases and accessories for
tightness.
o Rotate the fan wheels by hand to ensure no parts are
rubbing. If rubbing occurs, refer to Start-Up section
for more information.
o Confirm the EC motor voltage is correct. Reference
unit wiring diagram.
o Filters can load up with dirt during building
construction. Replace any dirty pleated filters and
clean the aluminum mesh filters in the intake hood
(refer to Routine Maintenance section).
o Verify that non-motorized dampers open and close
properly.
o Check the tightness of all factory wiring connections.
o Verify control wire gauge (refer to the Electrical
Connections section).
Start-Up Checklist
The unit will be in operational mode during start-up. Use
necessary precautions to avoid injury. All data must be
collected while the unit is running. In order to measure
volts & amps, the control center door must be open,
and the unit energized using a crescent wrench to turn
the disconnect handle.
o Check line voltage at unit disconnect
_______
L1-L2 volts
_______
L2-L3 volts
_______
L1-L3 volts
o Motor Amp Draw
• Supply Fan
_______
L1 amps
_______
L2 amps
_______
L3 amps
o Fan RPM
_______
Supply Fan
o Correct fan rotation direction
Supply Fan
Exhaust Fan
check as items are
• Exhaust Fan
______
L1 amps
______
L2 amps
______
L3 amps
______
Exhaust Fan
Yes / No
Yes / No
Energy Core Ventilator
13