Operation; Inverter Start-Up; Inverter Shutdown - YASKAWA SOLECTRIA XGI 1000-65/65 Installation And Operation Manual

Commercial 1000vdc string inverter
Hide thumbs Also See for SOLECTRIA XGI 1000-65/65:
Table of Contents

Advertisement

Installation and Operation Guide SOLECTRIA XGI 1000
Discovery: When inverters are connected in a Cluster it may take up to 10 minutes for all inverters to discover each
other.
Startup Wizard
Run the Startup Wizard by logging into one of the inverters and selecting Startup Wizard from the main menu.
Name the Inverters
Enter a name for each inverter on the list.
Configure the Reference List
Add or Remove the inverters from the reference list. This list consists of all inverters that are currently communicating
in the Cluster AND inverters that were previously added to the Reference List.
Select the Time Zone
Select the desired Time Zone from the dropdown list.
Choose a Cluster Name, SSID
A Cluster Name or SSID consists of three parts; the Site Name, Cluster ID, and WiFi channel. The Cluster Name generated
in this step will determine the WiFi SSID or WiFi network name.

Operation

Inverter Start-Up

Automatic Start-Up:
The inverter will start up automatically when the output voltage and power from the PV array meet the required values
and the AC grid is within the normal operating limits.
Manual Start-Up:
On the inverter page of the user interface, click the Connect to Grid button to turn the inverter ON.

Inverter Shutdown

Automatic Shutdown:
The inverter will shut down automatically when the output voltage and power of the PV array are lower than the
required values and when the AC grid is outside its normal operating limits.
Manual Shutdown:
On the inverter page of the user interface, click the Disconnect from Grid button to turn the inverter OFF.
DOCR-070733-F (2/22/2021)
INFO ✔
Page 63 of 78

Advertisement

Table of Contents
loading

Table of Contents