IBM 3454-FCE Customer Install Manual page 29

Cloud pak for data system
Table of Contents

Advertisement

 Chassis #1 - Install this 2U server (marked #1) one rack unit (1U) above the
bottom of the rack.
 Chassis #2 - Install this 2U server (marked #2) directly above Chassis #1.
 25G Switch - The 25G switch (marked # 3) should be installed above the top-
most server. You may install the 25G switch in any convenient location. (see
Figure 7 for recommended switch location, U24)
 1G Switch - The 1G switch (marked # 4) should be installed above the 25G
switch. You may install the 1G switch in any convenient location. (see Figure 7
for recommended switch location, U27)
 PDUs – Install horizontally at U33/U34 for easy cable routing and service access.
Additional PDUs should be installed above the PDUs at locations U35-U38.
 Other components like alternate 1U servers or spine switches should be installed
per the specific install guide included with those components.
Installation Notes:
 If you intend to expand your system, you may want to leave enough space
to install additional expansion chassis and switches at a later date. Expansion
chassis and switches are ordered separately. Expansion chassis and switches
can be racked in any order, but the preferred locations are shown in Figure 8.
Expansion PDUs should be installed above the base PDUs.
© Copyright IBM Corporation 2020.
Customer Install Guide, PDU
29