CAUTION
1 Always use the nitrogen.(not use oxygen, carbon dioxide, and
a Chevron gas): Please use the following nitrogen pressure
0.02MPa Oxygen – Promotes oxidative degradation of refrig-
erant oil. Because it is flammable, it is strictly prohibited to
use Carbon dioxide – Degrade the drying characteristics of
gas Chevron Gas – Toxic gas occurs when exposed to direct
flame.
2 Always use a pressure reducing valve.
3 Please do not use commercially available antioxidant.
The residual material seems to be the oxide scale is ob-
served. In fact, due to the organic acids generated by oxida-
tion of the alcohol contained in the anti-oxidants, ants nest
corrosion occurs. (causes of organic acid ' alcohol + copper
+ water + temperature)

REFRIGERANT PIPING INSTALLATION

Precautions on Pipe connection / Valve operation

Pipe connection is done by connecting from the end of the pipe to the
branching pipes, and the refrigerant pipe coming out of the outdoor
unit is divided at the end to connect to each indoor unit. Flare connec-
tion for the indoor unit, and welding connection for the outdoor pipe
and the branching parts.
- Use hexagonal wrench to open/close the valve.
Liquid pipe
Gas pipe
Refrigerant
Charging Port
WARNING
!
• Always careful not to leak the refrigerant during welding.
• The refrigerant generates poisonous gas harmful to human body
if combusted.
• Do not perform welding in a closed space.
• Be sure to close the cap of the service port to prevent gas leak-
age after the work.
CAUTION
!
• Please block the pipe knock outs of the front and side panels
after installing the pipes.
(Animals or foreign objects may be brought in to damage wires.)
• ARUV***BTS4 models do not have Refrigerant charging port.
Service Port
PIPE CONNECTIONS BETWEEN
INDOOR AND OUTDOOR UNIT
- Pipe connections can be done on the front side or on the side accord-
ing to the installation environments.
2
- Be sure to let 0.2kgf/cm
Nitrogen flow in the pipe when welding.
- If Nitrogen was not flown during welding, many oxidized membranes
may form inside the pipe and disturb the normal operations of valves
and condensers.
Right
Side Pipe
Draw Out
Left Side
Pipe Draw
Out
Front Pipe Draw Out

Preparation Work

- Use Knock Outs of Base Pan of the outdoor unit for Left/Right or
Bottom pipe drawing outs.
Removal Area for Liquid/Gas pipe
bottom side connections.
CAUTION
!
• Do not give damage to the pipe/base during the Knock Out
work.
• Proceed to pipe work after removing burr after Knock Out work.
• Perform sleeve work to prevent damage to the wire when con-
necting wires using knock Outs.
Remove leakage prevention cap
• Remove the leakage prevention cap attached to the outdoor unit
service valve before pipe work.
• Proceed the leakage prevention cap removal as follows:
- Verify whether the liquid/gas pipes are locked.
- Extract remaining refrigerant or air inside using the service port.
- Remove the leakage prevention cap
Liquid pipe
Gas pipe
Leakage Prevention Cap
Regulator
Refrigerant Pipe
Nitrogen
Nitrogen
Nitrogen
Direction
Direction
Direction
Taping
Valve
Nitrogen
Service Port
Refrigerant Charging Port