REMOVAL OF L - SHAPED LID
2.7
To remove the L-Shaped lid:
Remove all screws securing the lid.
Disengage the short return face of the lid as shown in Diagram 1.
Lift the lid up and off to access the controls as shown in Diagram 2.
To reassemble repeat the above process in reverse.
Diagram 1. Disengage short return
2.8

INSTALLATION OF HEATER

The Compact Classic range is designed to be installed in the roof or beneath the floor only.
This must be done in accordance with the following guidelines and AS 5601.
Installing in the Roof Space
The area under the heater must be capable of supporting the additional load, without causing deformation of
any part of the building structure
The appliance must be accessible by means of fixed access, a normal ladder or steps
A passage of 600mm wide must be provided between the roof access opening and the heater
This passage must have a suitable walkway of at least 19mm thick particle board or equivalent and be capable
of supporting the weight of a person and their tools
A permanent level platform must be provided beneath the heater and this platform area must extend 750mm out
from the controls access panel side and fan motor access panel side/s for the entire length of the heater
The air gap created between the base of the heater and the platform by the heater's supports must be
maintained
Permanent artificial lighting must be provided at the heater, with the switch located at the roof access opening
Installing Beneath the Floor
There must be a minimum clearance of 200mm between any part of the appliance and the lowest part of the
floor structure. In addition to this, refer to section "3.2 Service Clearances".
The heater must be located within 2m of the access opening, or there is to be a minimum clearance of 1.2m
between the lowest part of the floor structure and ground level, maintained from the access opening to the
heater
All under floor installations must be on a level concrete base (50mm thick), and provision made to drain any
seepage or ground water away from the heater
Permanent artificial lighting must be provided at the heater, with the switch located at the access opening
Lateral (horizontal) flues may be installed in accordance with AS 5601, making sure that the lateral flue section
has a minimum rise of a 20mm per metre of lateral run
The flue must be terminated outside the building in accordance with AS 5601. This termination can be
performed using a Brivis Remote Terminal. Refer to the Fluing instructions, "3.5 Flue Instructions"
Brivis
Diagram 2. Lift lid up and off
9