IBM SAN Volume Controller 2145-SV1 Hardware Installation Manual page 87

Table of Contents

Advertisement

Figure 50. Packaging materials
1
Enclosure
2
Top of shipping box, folded back.
3
Foam protectors
4. Remove the top cover, as described in "Removing the top cover: 2145-92F " on page 56.
5. With two or more persons, push the expansion enclosure sideways onto an adjacent flat bed lift.
Keep the remaining foam block protectors attached to the enclosure.
6. Remove the support rail kit from the box in which it was shipped (
54).
7. Separate the inner section of the support rails and attach them to each side of the expansion
enclosure, as described in steps "3" on page 58 through "5" on page 59 in "Installing or replacing
the support rails: 2145-92F " on page 57.
8. Attach the remaining sections of the support rails to the rack, as described in step "6" on page 59 in
"Installing or replacing the support rails: 2145-92F " on page 57.
9. Move the mechanical lift to the front of the rack. Align the inner section of the rails with the mid
section of the rails that are extending from the rack.
10. On each side, push the inner section and middle section of the rails together until they click and will
no longer separate, as described in step "1" on page 61 in "Installing or replacing an expansion
enclosure in a rack: 2145-92F " on page 61.
11. Remove the 4U and 1U fascia from the boxes in which they were shipped, as shown in Figure 51 on
page 56.
Chapter 4. Installing an optional 5U SAS expansion enclosure 55
1
, as shown in Figure 49 on page