Ceiling Suspended Units; Anchoring - Trane Performance Climate Changer PSCA Installation, Operation And Maintenance Manual

Table of Contents

Advertisement

Ceiling Suspended Units

(0<=Sds<=1.85)
The details for the suspension system, including the steel
members used to support the bottom of the unit, will need
to be determined by working directly with The VMC
Group. They will also help provide information regarding
the required external isolation system.

Anchoring

Lifting lugs should be used to anchor the unit at the ends
of each shipping split. Per the anchor requirements,
additional anchoring may be needed. If so, anchors will be
provided and installed on the unit. An example of a seismic
anchor is shown in
Figure
Anchor selection meets or exceeds IBC 2000,2003, 2006,
2009, 2012, and CBC 2007, 2010 compliance requirements.
Special Inspection per IBC Section 1704 is required on all
installations. All anchors listed above must be installed to
meet compliance.
Figure 43. Seismic anchor
CLCH-SVX013B-EN
43.
Figure 44. Seismic anchor pattern
AHU Plan View
Spacing <= 46 inches*
Spacing <= 46 inches*
*Only if not anchoring each functional section
AHU Elevation View
Section
Base rail
Installation - Mechanical
Staggered anchor
bolt patterns
Section
split
Section anchor
to base rail
Anchor bolt
to floor curb
33