Front Panel Installation
1. Lift and flex the panel outward and onto the base. Use
caution not to damage the battery box.
2. With wind rated units, install the two screws at (B).
3. Secure the panel with the two screws at (A).
Install the Roof
1. Carefully put the roof on the unit.
2. Install the screws (A) that secure the roof to the unit.
16
Fuel Installation Plan
WARNING
Propane and Natural Gas are extremely flammable
and explosive, which could cause burns, fire or explosion
resulting in death or serious injury.
• Installation must be performed by a licensed
professional.
• Install the fuel supply system according to NFPA 37 and
other applicable fuel-gas codes.
• Before placing the generator into service, the fuel
system lines must be properly purged and leak tested.
• NO leakage is permitted.
• DO NOT operate engine if smell of fuel is present.
NOTICE The supplied flexible fuel line is not to be
installed underground or in contact with the ground.
• The entire flexible fuel line must be visible for periodic
inspection and must not be concealed within nor contact
nor run through any wall, floor, or partition.
The information below is provided to assist gaseous fuel
system technicians in planning installations. In no way
should this information be interpreted to conflict with