Step 4. Fireplace should be secured to side
framing members using the full length nailing
tabs at the top and bottom of the fireplace front
face. Use 8d nails ( Figure 17 ).
8d Nail
Figure 17
Note: The nailing tabs and the area directly
behind the nailing tabs are exempt from the
clearances described on page 5. Maintain at
least 1/2" clearance from the firebox wrapper to
the framing at the closest point of contact,
directly adjacent to the flange.
For Canadian Installations
A cold Climate Kit FTF8-CCK3-LD must be
installed. CCK3 kits are available from
FireCraft through your local dealer. Installer
must supply suitable length of 6" Diameter,
class "0" metallic air duct.
Proceed with Steps 5 through 8
Step 5. Install the Cold Climate Kit to the
fireplace following the instructions provided
with the kit, ( Figure 18 ).
Figure 18
8
Step 6. Connect the 6" (102 mm) Class 0 air
duct provided by installer, to the duct collar on
the fireplace and secure with two (2) screws
from the kit's hardware package.
Step 7. Route the Class 0 air duct out the back
or side wall, up through the ceiling or floor
joists to an outside wall. The air inlet hood
should be located above snow level or above
any anticipated snow level, ( Figure 19 ).
Install As Shown With
Opening In Downward
Position Do Not Block
Figure 19
Note: If the fireplace is installed against an inside
wall, the class 0 air duct may be extended into a
ventilated attic space at least 18" (475mm) above
the attic floor. Secure the air inlet hood to a
vertical post with the inlet positioned downward.
Ensure that nothing blocks the hood opening.
This hood must never terminate higher than
three (3) feet below the termination.
Step 8. Cut or frame a hole through the outside
wall for the installation of the air inlet hood. A 6-
1/2" diameter hole is required. Feed the loose
end of the flexible duct through the hole and
attach to the collar on the air inlet hood using two
(2) screws from the kit's hardware package.
Insert the hood into the opening. Secure the inlet
hood in place with nails driven through the holes
in the flange. Seal with noncombustible water-
proof silicon type caulking.

INSTALLING THE CHIMNEY SYSTEM

Step 1. Before continuing, check the operation
of the damper, as described on page 4, ( refer to
Figure 3 ).
Step 2. Using standard construction framing
techniques, construct opening for chimney route
up through the ceiling(s) and roof or through an
outside chase.
Framing must maintain adequate minimum air
space clearance at all times.
NOTE: DIAGRAMS & ILLUSTRATIONS NOT TO SCALE.
CAUTION: ALLOW MINIMUM 1"* CHIMNEY
AIR SPACE TO COMBUSTIBLE FRAMING MEM-
BERS THROUGHOUT VERTICAL OR OFFSET
CHIMNEY INSTALLATION.
A minimum 1"* air space must be reserved for
all combustible materials extending for any
continuous length surrounding the chimney.
*Note: 2" clearance to combustibles required
in Canada.
Reference Figures 15 and 16 and charts Fram-
Entrance
ing Dimensions for Ceiling and Roof, which
specify minimum ceiling and roof dimensions.
In new construction, to determine chimney cen-
ter line, use plumb line from roof or ceiling above
fireplace to center of flue collar on fireplace.
5 Foot Min. Height
From Outside
For remodeling, plumb to center of flue collar
Ground Level
from ceiling above, drive nail through ceiling
from below to mark position, then mark and cut
to passage from above ceiling (around nail)
( Figure 20 ). Then plumb from ceiling or roof
level directly above hole which has just been
completed.
Figure 20
Step 3. Position appropriate firestop spacer at
ceiling and nail temporarily with two (2) 8d
nails. Use flat firestop spacer, Model F8FS-2, if
chimney penetrates ceiling vertically. If chim-
ney penetrates ceiling at 30 angle (offset chim-
ney), use 30 firestop spacer, Model F8FS30.
Use one nail on opposite sides to hold firestop
spacer in position. Nail permanently, using at
least two (2) more 8d nails, after chimney
sections have been assembled through the
firestop spacer and after any necessary adjust-
ments have been made. Firestop spacer must
be secured by at least four (4) 8d nails when
completely installed.