Chapter 3: Preinstallation checklist

Before you install the Ethernet Routing Switch 4900 Series, make sure that you complete the tasks
in the preinstallation checklist.
No.
Task
1.
Review the technical specification for the
switch. Make sure that the area where
you install the switch and where it will
operate meet the requirements.
2.
Verify the power supply unit (PSU)
specifications. Optionally order a
redundant PSU to provide redundancy
and load sharing.
3.
Make sure that you have the following
tools and cables:
• Phillips #2 screwdriver RJ-45 console
port cable
• ESD cable
4.
Unpack the equipment.
5.
Verify the contents of the shipped
package.
6.
Make sure that the power cord has the
correct country-specific termination.
7.
Prepare the rack.
February 2016
Description
For the physical, electrical, and
environmental specifications, see
Technical specifications
See
page 17.
See
Observe ESD precautions when you
unpack the equipment. See
discharge prevention
See
page 22 for a description of the
components that are provided with the
switch. If any components are missing,
contact Avaya support at
support.avaya.com/.
See
page 20.
Ensure that there is enough rack space
of 1.75 inches (4.45 centimeters).
Ensure that the rack is bolted to the floor
and braced if necessary.
Ensure that the rack is grounded to the
same grounding electrode used by the
Installing Avaya Ethernet Routing Switch 4900 Series
Comments on this document? infodev@avaya.com
on page 16.
AC power specifications
Cable requirements
on page 25.
Electrostatic
on page 15.
Verifying package contents
https://
AC power cord specifications
on
on
on
Table continues...
10

Advertisement

Table of Contents
loading

This manual is also suitable for:

4950gts4926gts-pwr+4926gts4950gts-pwr+

Table of Contents