Filling the loading cylinder on the DHW side
Fig. 16
1. Valves
A
and
B
must be in the "top" position.
2. Open the cold water line and a DHW draw-off
point.
Venting the boiler by flushing
Note
Inadequate venting can result in damage due to steam
blasts in the heat exchanger.
A
B
Commissioning, inspection, maintenance
3. Once air stops coming out of the DHW draw-off
point, the loading cylinder is completely filled.
21