3.1 Prepare The Unit For Installation
STEP 1 - Check for damage and report promptly to
the carrier any damage found to the unit.
Note: The unit is shipped "upside-down" in the
downflow orientation and may be easiest to trans-
port to the job site in that orientation. If the unit
must be transported in a horizontal position, it must
be laid on its back (marked "REAR" on carton).
Note: After the unit is removed from the carton,
depress the Schrader valve to verify coil is pressur-
ized.
3.2 Unit Accessories
Accessory Number
BAYEAAC05BK1A
BAYEAAC05LG1A
BAYEAAC08BK1A
BAYEAAC08LG1A
BAYEAAC10BK1A
BAYEAAC10LG1A
BAYEABC15BK1A
BAYEABC20BK1A
BAYEACC25BK1A
BAYSUPFLGA
BAYSUPFLGBA
BAYSUPFLGCA
BAYRETFLGAA
BAYRETFLGB
BAYRETFLGCA
TASB175
TASB215
TASB235
BAYSRKIT100A
BAYICSKIT01A
BAYHHKIT001A
BAYUVCLK001A
BAYLVKIT100A
6
Table 3.2
Description
Electric Heater, 5kW, Breaker, 24V Control, 1 Ph
Electric Heater, 5kW, Lugs, 24V Control, 1 Ph
Electric Heater, 8kW, Breaker, 24V Control, 1 Ph
Electric Heater, 8kW, Lugs, 24V Control, 1 Ph
Electric Heater, 10kW, Breaker, 24V Control, 1 Ph
Electric Heater, 10kW, Lugs, 24V Control, 1 Ph
Electric Heater, 15kW, Breaker, 24V Control, 1 Ph
Electric Heater, 20kW, Breaker, 24V Control, 1 Ph
Electric Heater, 25kW, Breaker, 24V Control, 1 Ph
Supply Duct Flange A
Supply Duct Flange B
Supply Duct Flange C
Return Duct Flange A
Return Duct Flange B
Return Duct Flange C
Plenum Stand A
Plenum Stand B
Plenum Stand C
Side Return Kit
Internal Condensate Switch Kit
Horizontal Hanger Kit
UVC Lights
Low Voltage Conduit Entry Kit
Fits Cabinet Size
A to C
A to C
A to C
A to C
A to C
A to C
B to C
B to C
C
A
B
C
A
B
C
A
B
C
A to C
A to C
A to C
A to C