Control Tapping Locations - Steam Boilers - Weil-McLain 94 Series Manual

Water & steam boilers for use with gas, light oil, & gas/light oil-fired burners
Hide thumbs Also See for 94 Series:
Table of Contents

Advertisement

Boiler manual:
• Installation
Control tapping locations — steam boilers
Figure 11
Model 94 steam boiler control tappings
Item #
Function
PRESSURE TEST GAUGE — REMOVE AFTER
J1
HYDROSTATIC TEST
J1 + J5
Gauge glass
J2
PLUG this tapping — not used
PLUG this tapping — not used
M3
M1 + M2
Float-type low water cutoff, LWCO/pump control or
LWCO/feeder combination
M3 + M4
P1
Skim tapping
P2
Steam pressure relief valve
R1
Skim tapping
R2
Steam pressure relief valve
Steam pressure gauge — or —
S1
Pressure controls (limit, operating, etc.)
S2
Pressure controls (limit, operating, etc.)
T1 or T2
Pressure controls (limit, operating, etc.)
Steam pressure gauge — or —
T3 or T4
Pressure controls (limit, operating, etc.)
Steam pressure relief valve — Install relief valve in
U1 or U2
one tapping and plug the other
Steam pressure relief valve — or —
V1 or V2
Skim tapping
Steam pressure gauge — or —
W1 or W2
Pressure controls (limit, operating, etc.)
W3 or W4 Pressure controls (limit, operating, etc.)
X1 & X2
PLUG these tappings — not used
X3 & X4
PLUG these tappings — not used
Y1 & Y2
Try cocks
Cleanout tappings — Front section — Install 2" NPT
Z1 or Z2
close nipple and 2" NPT cap in each cleanout tapping
Cleanout or drain tappings — Rear section —
Z3 or Z4
Install drain valve in one tapping; install 2" NPT x 2½"
length nipple and 2" NPT cap in the other
Low limit temperature control (when using tankless
heaters) — locate in control tapping on one of the tankless
heaters
Controls and fi ttings must not
obstruct cleanout openings or
prevent required access to the
boiler or components.
Part No. 550-110-275/1018
• Start-Up
• Maintenance
Size
(Inches
NPT)
½
½
½
1
1
3
3
4
4
¾
¾
2
4
¾
¾
3
8
2
2
• Parts
13