Start Up And Information For Use; Command Components - Tauler SmartMatic 2.0 Operating Manual

The sheet paper and cardboard thermo plastic laminating machine
Table of Contents

Advertisement

START UP AND INFORMATION FOR USE

In order to carry out the start up process, the following steps must be taken:
1. - Unpack machine from the box in which TAULER delivers it.
2. - Lower machine from the box using a fork lift truck capable of lifting 850
kg.
3. - Plug the machine to a three phasic connection 380/400V using the cable
supplied with the machine.
AN INCORRECT CONECTION COULD CAUSE SERIOUS DAMAGE TO
THE ELECTRICAL SYSTEM OF THE MACHINE. IT IS
RECOMMENDED THAT THIS CONECTION PROCESS IS CARRIED
OUT BY SPECIALISED PERSONNEL
4. - Plug the machine to an air supply source (compressor), using the pipe
supplied with the machine.
5. - Switch ON the machine.
6. - Re-arm the safety button.
The machine is now ready for operation.

COMMAND COMPONENTS

1. - Electronic temperature controller.
2. - Emergency reset button.
3. - Emergency stop button.
4. – Pressure regulators.
[Technical Documentation]