Piping Installation; Optional Gas Piping; Gas Connections; Optional Coil Piping - Greenheck VersiVent VER-45 Installation, Operation And Maintenance Manual

Energy recovery ventilator
Table of Contents

Advertisement

Piping Installation

Optional Gas Piping

Units with indirect gas-fired furnaces require field-
supplied and installed gas supply piping. The unit gas
connection is
inch NPT. The maximum allowable gas
3
4
pressure is 14 in. wg.
Gas Cock
From Gas Supply
Bleeder Valve or
1/8 in Plugged Tap
Typical Gas Supply Piping Connection

Gas Connections

If this unit is equipped with an indirect gas-fired furnace,
connection to an appropriate gas supply line will be
required. For complete information on installation
procedures for the optional gas furnace, refer the
PVF/PVG Indirect Gas-Fired Heat Module Installation,
Operation, and Maintenance Manual.

Optional Coil Piping

Factory-installed cooling and heating components are
mounted in the coil section of the unit. The coil section
is downstream of the energy wheel on the supply air
side of the unit. Note the coil connection locations. Coil
connections are located external to the unit as shown.
DX coil liquid
connection
access door
Note: DX coil liquid connection is internal to units.
Ground
Gas to
Joint
Controls
Union
8 in. Trap
Water coil
connections

Water Coils

1. Piping should be in accordance with accepted
industry standards. Pipework should be supported
independently of the coils. When installing couplings,
do not apply undue stress to the connection
extending through the unit. Use a backup pipe
wrench to avoid breaking the weld between coil
connection and header.
2. Connect the water supply to the bottom connection
on the air leaving side and the water return to the
top connection on the air entering side. Connecting
the supply and/or return in any other manner will
result in very poor performance. Be sure to replace
factory-installed grommets around coil connections
if removed for piping. Failure to replace grommets
will result in water leakage into the unit and altered
performance.
3. Water coils are not normally recommended for
use with entering air temperatures below 40°F. No
control system can be depended on to be 100% safe
against freeze-up with water coils. Glycol solutions
or brines are the only safe media for operation of
water coils with low entering air conditions. If glycol
or brine solutions are not used, coils must be drained
when freezing conditions are expected. If required,
vent and drain connections must be field-
piped, external to the unit.
4. Pipe sizes for the system must be selected on
the basis of the head (pressure) available from the
circulation pump. The velocity should not exceed
6 feet per second and the friction loss should be
approximately 3 feet of water column per 100 feet
of pipe.
5. For chilled water coils, the condensate drain
pipe should be sized adequately to ensure the
condensate drains properly.
Direct Expansion (DX) Coils (Split DX)
1. Piping should be in accordance with accepted
industry standards. Pipework should be supported
independently of the coils. Undue stress should not
be applied at the connection to coil headers.
2. The condensate drain pipe should be sized
adequately to ensure the condensate drains properly.
Refer to Condensate Drain Trap section.
3. When connecting suction and liquid connections
make sure the coil is free from all foreign material.
Make sure all joints are tight and free of leakage. Be
sure to replace factory-installed grommets around
coil connections if removed for piping.
4. Manufacturer does not supply compressor or
condensing units with standard models. For further
instruction on DX coil installation and operation
contact your compressor and/or condenser
manufacturer.
VersiVent Energy Recovery Ventilator
15

Advertisement

Table of Contents
loading

This manual is also suitable for:

Versivent ver-90Versivent ver-65

Table of Contents